Auditing before the ribbon is cut

A pre-go-live reading is useful when the vendor says ready and the rooms manager still cannot run a discrepancy report on a dry-run house.

Night view of a hotel driveway and entrance canopy

Openings in the Klang Valley often share a pattern: the PMS is configured against a demo property, the door locks are installed by a different contractor, and the POS goes live in the coffee house two days before rooms. Each vendor is ready. The path between them is not.

We join the last rehearsals. A dry-run occupancy of twenty rooms, with a night audit and a handful of room charges, tells us more than a project plan. If the discrepancy report is blank because nobody created a vacant-dirty room, the opening team has not yet seen the report they will need on night two.

Public holidays matter. If vendor support is in another time zone and the opening sits beside a Malaysian holiday, the fallback is paper and manual keys. We ask to see those keys, and who is allowed to issue them, before we write a go-live note.

The deliverable is a stop/go list, not a celebration. Some paths can wait until week three. Some cannot: posting a rate that does not exist, a lock that does not encode, a payment device that is still in training mode. Those stay on the first page.

If this sounds like your property, request a briefing